Question 8 0 5 p t s A contractor has agreed to build 1 0 dog houses in 2 0 days at a price of
Question
A contractor has agreed to build dog houses in days at a price of $ per unit. days later, the contractor has finished dog houses with an actual total cost of $ What is the cost variance ACWP
$
$
$
$