Question
Question 8 Given the following cash flow of the baseline budget, What is the estimate of escalated cash out flow and escalation % of the
Question 8
Given the following cash flow of the baseline budget, What is the estimate of escalated cash out flow and escalation % of the baseline? Hint: See Table 11.4 (Raydugin, p. 222) for example of calculation of the Cost Escalation Reserve.
Account | Estimate | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 |
Adjusted Composite Index | NA | 1.000 | 1.050 | 1.400 | 1.600 | 2.000 | 1.700 | 0.900 |
Cash Outflow (Base) | 175000 | 50000 | 40000 | 30000 | 20000 | 14000 | 11000 | 10000 |
Cash Outflow (Escalated) | ? | |||||||
Escalation % | ? |
Question 8 options:
A | Escalated cash out flow = 123050 Escalation % = 17.5% |
B | Escalated cash out flow = 2000000 Escalation % = 127.5% |
C | Escalated cash out flow = 223050 Escalation % = 27.5% |
D | Escalated cash out flow = 221700 Escalation % = 26.7% |
E | It is not possible to calculate escalated cash outflow. |
Question 1
A particular uncertainty may be managed at more than one level. Which of the followingstatements arerecommended regarding the promoting and demoting of uncertainties? (Select all that apply)
A | Game changers and show-stoppers should be listed in the business-unit (or even corporate) register |
B | Medium-level/material/yellow uncertainties should be placed in either discipline or project registers |
C | Low-level/small/green uncertainties should stay in discipline logs/registers |
D | High-level/critical/red uncertainties should be shown in both project and business-unit registers |
E | The promoting of critical uncertainties is necessary only if you think the project manager or business unit managers are capable of dealing with them. |
Question 2
A particular uncertainty may be managed at more than one level. Which of the followingstatements are notrecommended regarding the promoting and demoting of uncertainties? (Select all that apply)
Question 2 options:
A | The promoting of critical uncertainties is necessary only if you think the project manager or business unit managers are capable of dealing with them. |
B | Medium-level/material/yellow uncertainties should be placed in either discipline or project registers |
C | High-level/critical/red uncertainties should be managed at the work package level andnever be promoted to upper levels if you think it will have a significant impact on company objectives and your job |
D | Low-level/small/green uncertainties shouldalways be promoted to the businessunit level risk register |
E | Game changers and show-stoppers should be listed in the business-unit (or even corporate) register |
Question 3
Which of the following findings of a risk management health self-check would be considered unacceptable for project reserves and execution plan integration? (select all that apply)
Question 3 options:
A | Existing risk register not updated or used as a basis of probabilistic risk analysis for development of project reserves. |
B | Risk management integrated as part of project execution plan. |
C | Project reserves are not tracked and drawn down. |
D | Risk register not used for development of project reserves. |
E | Cost escalation modelnot developed or considered a factor. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started