Question 8 There are five activities in making one toy: cutting, sewing, stuffing, assembling, and packaging. The activities have to be carried out in this
Question 8
There are five activities in making one toy: cutting, sewing, stuffing, assembling, and packaging. The activities have to be carried out in this order. The processing time of each activity is given below:
Activity | Processing time (minutes per toy) |
Cutting | 15 |
Sewing | 8 |
Stuffing | 8 |
Assembling | 10 |
Packaging | 5 |
Demand rate is 4 toys per hour. Currently we have worker A in charge of cutting and sewing, worker B in charge of stuffing, and worker C in charge of assembling and packaging. Which of the following strategies will increase the process capacity by balancing the line ?
Group of answer choices
Adding one additional worker to cutting.
Adding two additional workers to assembling.
Moving sewing to worker B.
Moving packaging to worker A.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started