Question 9 4 pts Based on the information in the table, what is Project A's MIRR? Project A Year Cash-flow 0 -$295 1 $269 2
Question 9 4 pts Based on the information in the table, what is Project A's MIRR? Project A Year Cash-flow 0 -$295 1 $269 2 $249 3 $203 14 -$147 5 Cost of project 3.21% WACC 6.25% Question 10 4 pts Based on the information in the table, what is Project A's MIRR? Calculate your answer as a percentage to 2 decimal places (e.g., 5.22) Project A Year Cash-flow 0 - $251 1 $53 2 $52 3 $100 4 5 Cost of project 4.49% WACC 6.73%