Question

1 Approved Answer

Question 9 Critical path is the _ _ _ _ _ _ _ _ _ _ _ _ _ _ path to complete the project

Question 9
Critical path is the ______________ path to complete the project in ________ possible duration.
1 point
Longest, shortest
Shortest, longest
Longest, longest
Shortest, shortest