QUESTION a) Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform the CPM calculation
QUESTION
a) Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform the CPM calculation using the forward pass and backward pass methods and complete Table 1(b).
b) Draw a resource profile (histogram) following the scenarios below and determine how to level the resources. Give your comments on the resource profile.
i ) Only 10 labourers available at any time
ii ) Only 8 labourers available, but a peak use of 10 labourers is allowed for one time (one day) only
TABLE 1 (a)
\fActivity Activity Description IPA* Duration (Days) Labour Excavation & A 4 foundation B SOG A 3 C Framing 10 D Plumbing E Electrical wiring Drywall m MOOOOL HVAC H Roof IN W N N W A W W N - Paint C HVAC Finish G, H K Flooring D, I L Electrical finish E, H M Punch list & cleanup / J, K, L 1Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started