QUESTION a) Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform the CPM calculation

QUESTION

a) Draw the Critical Path Method (CPM) network diagram and highlight the critical path for activities shown in Table 1(a). Perform the CPM calculation using the forward pass and backward pass methods and complete Table 1(b).

b) Draw a resource profile (histogram) following the scenarios below and determine how to level the resources. Give your comments on the resource profile.

i ) Only 10 labourers available at any time

ii ) Only 8 labourers available, but a peak use of 10 labourers is allowed for one time (one day) only

TABLE 1 (a)

image text in transcribedimage text in transcribed
\fActivity Activity Description IPA* Duration (Days) Labour Excavation & A 4 foundation B SOG A 3 C Framing 10 D Plumbing E Electrical wiring Drywall m MOOOOL HVAC H Roof IN W N N W A W W N - Paint C HVAC Finish G, H K Flooring D, I L Electrical finish E, H M Punch list & cleanup / J, K, L 1

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Motivated

Authors: For Goodness Sake Network

1st Edition

B0CNMLYFJ3

More Books

Students also viewed these General Management questions

Question

Differentiate tan(7x+9x-2.5)

Answered: 1 week ago

Question

Explain the sources of recruitment.

Answered: 1 week ago

Question

Differentiate sin(5x+2)

Answered: 1 week ago

Question

Compute the derivative f(x)=1/ax+bx

Answered: 1 week ago

Question

=+ How does this differ from the Solow model?

Answered: 1 week ago