Question at position 4 The budgeted labour cost of producing 3,500 units of Gauta for quarter one was 2,565.50. Each unit should take six minutes
Question at position 4 The budgeted labour cost of producing 3,500 units of Gauta for quarter one was 2,565.50. Each unit should take six minutes of labour to make at a cost of 7.33 per hour. The actual labour cost for quarter one was 3,200 and 4,000 units were produced. Using flexed budget, what is the labour rate variance?