Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question Completion Status: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Question Completion Status: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 During planning, the team has identified the items in the following table as work to be done on the project. Draw a network diagram to graphically depict this flow. All relationships are F-S relationships and durations are in days. Work Package Duration (Days) Predecessors A. Plan move 20 Start B. Complete internal construction to 45 A final floor plan C. Hold kickoff meeting 1 A D. Select furniture 25 C E. Prepare office for move 20 C F. Order new signs 15 C G. Set up utilities (wiring, and so on) 30 A H. Install new furniture/communications 10 B, D equipment/computers 1. Move/relocate 5 H, E, G J. Close out project 5 I, F What is the Critical Path? WhatsApp Image...jpeg WhatsApp Image...jpeg A WhatsApp Image...jpeg WhatsApp Image...jpeg Show all X O WE 6:43 PM CA 250C ~ 8 0 (( 41) ENG 2022-08-172 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 During planning, the team has identified the items in the following table as work to be done on the project. Draw a network diagram to graphically depict this flow. All relationships are F-S relationships and durations are in days. Work Package Duration (Days) Predecessors A. Plan move 20 Start B. Complete internal construction to 45 A final floor plan C. Hold kickoff meeting 1 A D. Select furniture 25 C E. Prepare office for move 20 C F. Order new signs 15 C G. Set up utilities (wiring, and so on) 30 A H. Install new furniture/communications 10 B, D equipment/computers 1. Move/relocate 5 H, E, G J. Close out project 5 I, F What is the duration of the project? WhatsApp Image...jpeg WhatsApp Image..jpeg WhatsApp Image...jpeg WhatsApp Image..jpeg Show all X2 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 During planning, the team has identified the items in the following table as work to be done on the project. Draw a network diagram to graphically depict this flow. All relationships are F-S relationships and durations are in days. Work Package Duration (Days) Predecessors A. Plan move 20 Start B. Complete internal construction to 45 A final floor plan C. Hold kickoff meeting 1 A D. Select furniture 25 C E. Prepare office for move 20 C F. Order new signs 15 C G. Set up utilities (wiring, and so on) 30 A H. Install new furniture/communications 10 B, D equipment/computers 1. Move/relocate 5 H, E, G J. Close out project 5 I, F What is Early finish (EF) of task I (Move/relocate)? WhatsApp Image...jpeg WhatsApp Image....jpeg WhatsApp Image...jpeg WhatsApp Image...jpeg2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 During planning, the team has identified the items in the following table as work to be done on the project. Draw a network diagram to graphically depict this flow. All relationships are F-S relationships and durations are in days. Work Package Duration (Days) Predecessors A. Plan move 20 Start B. Complete internal construction to 45 A final floor plan C. Hold kickoff meeting 1 A D. Select furniture 25 C E. Prepare office for move 20 C F. Order new signs 15 C G. Set up utilities (wiring, and so on) 30 A H. Install new furniture/communications 10 B, D equipment/computers 1. Move/relocate 5 H, E , G J. Close out project 5 I, F What is Early start (ES) of task D (Select furniture)? WhatsApp Image..jpeg WhatsApp Image....jpeg WhatsApp Image...jpeg WhatsApp Image...jpeg Show all O WE CA 25.C ~ (8 0 (7 41)) ENG 6:46 PM 2022-08-172 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Work Package Duration (Days) Predecessors A. Plan move 20 Start B. Complete internal construction to 45 A final floor plan C. Hold kickoff meeting A D. Select furniture 25 C E. Prepare office for move 20 C F. Order new signs 15 C G. Set up utilities (wiring, and so on) 30 A H. Install new furniture/communications 10 B. D equipment/computers 1. Move/relocate 5 H, E, G J. Close out project 5 I , F What is the float of Task E (Prepare office move)? For the toolbar, press ALT+F10 (PC) or ALT+FN+F10 (Mac). D T Acial T WhatsApp Image..jpeg WhatsApp Image...jpeg WhatsApp Image...jpeg WhatsApp Image..jpeg
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started