Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question content area Part 1 The latest finish of an activity is Part 2 A . ES + Activity time. B . Max { EF

Question content area
Part 1
The latest finish of an activity is
Part 2
A.
ES+ Activity time.
B.
Max{EF of all immediate predecessors}.
C.
LFminusActivity time.
D.
Min{LS of all immediate following activities}.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel Jr.

8th edition

470533021, 978-0470533024

More Books

Students also viewed these General Management questions