Question content area Part 1 Which column in Microsoft Project defines the precedence relationships among the activities? Part 2 A . successors B . predecessors
Question content area
Part
Which column in Microsoft Project defines the precedence relationships among the activities?
Part
A
successors
B
predecessors
C
order
D
relations