Question Content Area Reynolds Manufacturers Inc. has estimated total factory overhead costs of $100,000 and expected direct labor hours of 12,500 for the current fiscal
Question Content Area
Reynolds Manufacturers Inc. has estimated total factory overhead costs of $100,000 and expected direct labor hours of 12,500 for the current fiscal year. If job 117 incurs 1,370 direct labor hours, Work in Process will be debited and Factory Overhead will be credited for
a.$1,370
b.$50,000
c.$10,960
d.$100,000