Question

1 Approved Answer

Question : Daily demand (constant) = 10 Average lead time = 6 days Standard deviation of lead time = LT = 3 98% service level

Question :

Daily demand (constant) = 10

Average lead time = 6 days

Standard deviation of lead time = LT = 3

98% service level desired .

Find ROP?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management

Authors: Harvey maylor

4th Edition

027370432X, 978-0273704324

More Books

Students also viewed these General Management questions

Question

19. What do you think the future of ISDN holds? Why?

Answered: 1 week ago

Question

16. How is a virtual circuit distinguished from other circuits?

Answered: 1 week ago