Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question Description You are the general manager of a large construction project. The contract has both financial incentives for finishing on time or early as
Question Description You are the general manager of a large construction project. The contract has both financial incentives for finishing on time or early as well as large penalties if the project is completed late. You know that to get it done on time or early, project planning using a formal time line is essential. Address the following questions: 1) In terms of creating a timeline, what is meant by the critical path of a PERT chart? 2) As a project manager you know that the fastest possible time a project can be completed is known as the critical path. This implies that any delay in any step of a projects critical path, will therefore delay the overall project. On a particular project, step B is part of the critical path; step C and D both are not. Assume that all of these steps, B, C, and D are at risk of being delayed due to some issue (could be lack of people, lack of materials, equipment downtime-it makes no difference)- How would the manager go about prioritizing correction of the problem existing in B, C or D? - Should the manager address the issue in step B first step C first, or step D first; why? 3)Once repair is completed in step #2, how would go you about prioritizing repairs at the other two steps? Question Description You are the general manager of a large construction project. The contract has both financial incentives for finishing on time or early as well as large penalties if the project is completed late. You know that to get it done on time or early, project planning using a formal time line is essential. Address the following questions: 1) In terms of creating a timeline, what is meant by the critical path of a PERT chart? 2) As a project manager you know that the fastest possible time a project can be completed is known as the critical path. This implies that any delay in any step of a projects critical path, will therefore delay the overall project. On a particular project, step B is part of the critical path; step C and D both are not. Assume that all of these steps, B, C, and D are at risk of being delayed due to some issue (could be lack of people, lack of materials, equipment downtime-it makes no difference)- How would the manager go about prioritizing correction of the problem existing in B, C or D? - Should the manager address the issue in step B first step C first, or step D first; why? 3)Once repair is completed in step #2, how would go you about prioritizing repairs at the other two steps
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started