Question six a) Define a project budget b) Differentiate between planned value and actual value c) A 12-month project is in its 6th month (50%

Question six

a) Define a project budget

b) Differentiate between planned value and actual value c) A 12-month project is in its 6th month (50% of the time has been used), but has accomplished only 40% of its activities and has spent 60% of its financial resources according to the latest financial report. The total budget for the projects is $2,400,000.

Calculate

i) Planned value

ii) Actual cost

iii) Earned value

iv) Cost variance

v) Schedule variance

vi) Cost performance index

vii)Schedule performance index

How can a project manager know if his project is on track or not?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting for Governmental and Nonprofit Entities

Authors: Jacqueline L. Reck, James E. Rooks, Suzanne Lowensohn, Daniel Neely

18th edition

1260190080, 1260190083, 978-1259917059

Students also viewed these General Management questions

Question

Can a direct access file be read sequentially? Explain.

Answered: 1 week ago