Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question TASK NAME PRODECESSOR DURATION A - 3 B A 4 C A 2 D B 7 E B 6 F C 4 G D
Question
TASK NAME | PRODECESSOR | DURATION | |
A | - | 3 | |
B | A | 4 | |
C | A | 2 | |
D | B | 7 | |
E | B | 6 | |
F | C | 4 | |
G | D | 5 | |
H | E,F | 2 | |
I | H | 3 | |
J | G,I | 4 |
Using the information in the network diagram created using the details above, identify the critical path tasks:
Task #1: (first task on the critical path)
Task #2: (second task on the critical path)
Task #3: (third task on the critical path)
Task #4: (fourth task on the critical path)
Task #5: (fifth task on the critical path)
What is the total length (in days) of this project's tasks?
Using the information in the network diagram, what is the Total Float / Slack available on each of these tasks:
Task C:
Task D:
Task E:
Task F:
Task H:
Task I:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started