Question: The following details are provided for a company operating a process costing system: - Process 1 Opening work in process (WIP) Nil Units introduced
Question:
The following details are provided for a company operating a process costing system: -
Process 1
Opening work in process (WIP) Nil
Units introduced into the process 15,000
Units completed and transferred to next Process 2 10,000
Closing WIP (50% complete) 5,000
Materials cost (introduced at start of process) RM70,000
Conversion cost RM50,000
Process 2
Opening WIP Nil
Units transferred from Process 1 10,000
Closing WIP (50% complete) 1,000
Completed units transferred to finished goods stock 9,000
Previous process cost RM95,000
Conversion costs RM55,000
Materials (introduced at the end of the process) RM35,000
Required:
(a)Compute the equivalent units and cost per equivalent unit for the month for Processes 1 and 2.(16 marks)
(b)Prepare the cost allocation for Processes 1 and 2.(9 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started