QUESTION TWO [ 2 0 ] EC , an engineering company, produces tools and components to customers' specific requirements. EC uses absorption costing to absorb
QUESTION TWO
EC an engineering company, produces tools and components to customers' specific requirements. EC uses absorption costing to absorb overheads into the cost of each customer order. Selling prices are usually determined by adding a mark up to the costs incurred in completing the order.
EC has recently been asked to provide a quotation for a new customer. The details of the work have been discussed at a meeting with the customer and the following resource requirements have been determined. The cost of these resources has been calculated using the companys routine costing system.
Note
R
Direct material A
square metres @ R
Direct material B
square metres @ R
Skilled labour
hours @ R
Unskilled labour
hours @ R
Supervision labour
hours @ R
Machine overhead
hours @ R
Other overhead
labour hours @ R
Total cost
Notes:
Direct material A is currently held in inventory and is in regular use. The latest price paid for material A was R per square metre, but the replacement cost would be R per square metre.
Direct material B is currently not used by EC and would have to be bought if the work is undertaken. The minimum order from the supplier of material B is for square metres. EC does not expect to be able to use this material on any other work, though it would be able to sell it as scrap for R per square metre.
The skilled labour that would be required is available within EC but only if those employees are transferred from other work that they are currently doing. This other work could be done by subcontractors who could be hired on an hourly basis at a cost of R per hour. Alternatively subcontractors could be hired to work on this new customers order at a cost of R per hour. ECs current skilled labour is paid R per hour.
The unskilled labour is paid an hourly rate of R but only for hours that they are actively working. There are only hours of additional unskilled labour available within normal working hours. In order to complete the customer order on time they would have to work hours of overtime. EC pays an overtime premium of
The work would be supervised by the existing supervisor as part of his normal activity. The supervisor is paid an annual salary which is equivalent to R per hour for a hour working week.
The machines that would need to be used have a running cost of R per hour. Two different machines would be required: machine W for hours and machine Z for hours. Both machines are regularly used by EC Machine W is very specialised and is used for only some of ECs work. There is sufficient spare capacity on this machine. Machine Z is in constant use by EC and, if it is required for this customer order, EC would need to hire an additional machine at a hire cost of R per hour excluding running costs to fulfill its normal work.
ECs nonmachine related fixed overhead costs are absorbed into product costs using an absorption rate per labour hour.
If this customer order is accepted it must be completed during the next days.
EC would like to win this order as it believes that it will probably win repeat orders from the customer. The directors have therefore decided to price this work on the basis of its relevant cost plus
REQUIRED:
Prepare a schedule that shows the relevant cost of the new customer's order.
Explain, for each of the resource items numbered to the reason for each of the values you have included in your answer to above.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started