Question When analyzing the contractor's cumulative Cost Performance Index (CPICum) and To Complete Performance Index for the Estimate at Completion (TCPIEAC), Which of the following
Question
When analyzing the contractor's cumulative Cost Performance Index (CPICum) and To Complete Performance Index for the Estimate at Completion (TCPIEAC), Which of the following is correct
Possible answers
1.At contract completion, the CPICUM will equal the TCPIEAC because ACWP will be equal to BCWS.
2.If the trend lines of the CPI and TCPI are diverging, then the likelihood of achieving the EAC target is decreasing.
3. If the general trend of the contractor's cumulative CPI is sloping downward, then it is getting better.
4.If the contractor's cumulative CPI is greater than the TCPI, then the EAC is less likely to be achievable than if the CPI is less than the TCPI.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started