Question01 Problem Statement: Project Control and Monitoring You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its
Question01
Problem Statement: Project Control and Monitoring
You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project.
Required:
- [02 marks] Calculate Cost and Schedule Variance
- [02 marks] What is SPI and CPI of the project?
- [02 marks] Estimate at completion and Estimated time to complete?
Question02
Problem Statement: Procurement Management
Aisha wants to join Pakistans biggest construction firm as a project manager. She is giving a case study to read it thoroughly so that a discussion could be made on this as part of interview. The project was about to construct a road between two mega cities. It was a mega project involving a lot of contracts with different vendors. The project manager had made a number of cost plus fixed fee (CPFF) type of contracts with multiple vendors. For example, a contract was made with a vendor to lease a machine. The cost of leasing the equipment is 1200 $ per day while the cost of an outright purchase is 96000 $ and a daily maintenance cost of 200 $.The duration of completing the activity for which this equipment was leased is 150 days. No evidence of contract closing were found in the documentation of project. The firm and their sponsors bear a loss at the completion of this project.
Required:
Identify all the mistakes made by the project manager by providing proper justification.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started