Question

1 Approved Answer

QUESTION#1 A partially solved PERT problem is detailed in the table. below. Times are given in weeks. Optimistic Probable Pessimistic Expected Activity Preceding Time

image text in transcribed

QUESTION#1 A partially solved PERT problem is detailed in the table. below. Times are given in weeks. Optimistic Probable Pessimistic Expected Activity Preceding Time Time Time Time Variance A -- 7 9 14 1.361 B A 2 2 8 0 C A 8 12 16 0 D A 3 5 10 1.361 E B 4 6 8 0 F B 6 8 10 0 G C, F 2 3 4 0 H D 2 2 8 1.000 I H 6 8 16 2.778 J G, I 4 6 14 2.778 K E, J 2 2 5 0.250 a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above. b. C. Which activities form the critical path? What is the estimated time of the critical path? What are the project variance and the project standard deviation? d. e. What is the probability of completion of the project after week 40?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective small business management An Entrepreneurial Approach

Authors: Norman M. Scarborough

10th Edition

132157462, 978-0132157469

More Books

Students also viewed these General Management questions

Question

How well did your team handle differences of opinion?

Answered: 1 week ago