Answered step by step
Verified Expert Solution
Question
1 Approved Answer
QUESTION#1 A partially solved PERT problem is detailed in the table. below. Times are given in weeks. Optimistic Probable Pessimistic Expected Activity Preceding Time
QUESTION#1 A partially solved PERT problem is detailed in the table. below. Times are given in weeks. Optimistic Probable Pessimistic Expected Activity Preceding Time Time Time Time Variance A -- 7 9 14 1.361 B A 2 2 8 0 C A 8 12 16 0 D A 3 5 10 1.361 E B 4 6 8 0 F B 6 8 10 0 G C, F 2 3 4 0 H D 2 2 8 1.000 I H 6 8 16 2.778 J G, I 4 6 14 2.778 K E, J 2 2 5 0.250 a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above. b. C. Which activities form the critical path? What is the estimated time of the critical path? What are the project variance and the project standard deviation? d. e. What is the probability of completion of the project after week 40?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started