Questions 5 A company needs to manage a project that consists of the following set of activities: Activity Normal Time to Complete (Day) Immediate
Questions 5 A company needs to manage a project that consists of the following set of activities: Activity Normal Time to Complete (Day) Immediate Predecessor A 2 B 3 A C 5 B D 3 C E 2 B F 4 E G 2 D, F The project network is shown below. Based on normal completion time, please determine the EST, EFT and LST, LFT of each activity in following table (next page). What is the critical path? D start A B finish E F Activity EST EFT LST LFT A 0 2 0 2 B 2 5 C D E F G 13 15