Question

1 Approved Answer

Quickbuild Ltd entered into a two-year contract on 1 January 20X7 at a contract price of 250,000. The estimated cost of the contract was 150,000.

Quickbuild Ltd entered into a two-year contract on 1 January 20X7 at a contract price of 250,000. The estimated cost of the contract was 150,000. At the end of the first year the following information was available:

contract costs incurred totalled 70,000

inventories still unused at the contract site totalled 10,000

progress payments received totalled 60,000

other non-contract inventories totalled 185,000.

Required:

(a) Calculate the statement of comprehensive income entries for the contract revenue and the contract costs.

(b) Calculate entries in the statement of financial position for the amounts due from construction contracts and inventories.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

How To Secure And Audit Oracle 10g And 11g

Authors: Ron Ben-Natan, Brian E. White, Paul R. Garvey

1st Edition

1420084127, 978-1420084122

More Books

Students also viewed these Accounting questions

Question

Presentation Aids Practicing Your Speech?

Answered: 1 week ago