quickly The process design team at a manufacturer has broken an assembly process into eight basic tasks, each with a required time and predecessor as
quickly The process design team at a manufacturer has broken an assembly process into eight basic tasks, each with a required time and predecessor as shown in the table. They work 7 hours a day and want to produce at a rate of 360 units per day. Task Time (sec) Predecessor A 40 B 35 A 30 D 40 B, C E 25 D F 50 D G 20 E H 30 F G Total 270 (sec) If you were assigning tasks based on the "most following tasks" rule, how many following tasks does task E have