Question: Quiz na a. Consider the following processes with arrival time and burst time. Draw the Gantt Chart [2 marks] b. Calculate Waiting time of each
Quiz na a. Consider the following processes with arrival time and burst time. Draw the Gantt Chart [2 marks] b. Calculate Waiting time of each process [ 1.5 Marks) c. Calculate Total Waiting Time [0.5 Mark] d. Average waiting time [1 mark] Sect Obje - 25 2 2. 7 13 14 19 IS using round robin scheduling with time quantum 2 ms? Process id Burst time (ms) QI 4 Q2 3 Q3 6 25 3 04 1 Sec Ans 25