Question: Consider the following processes with arrival time and burst time. a. Draw the Gantt Chart [ 2 Marks] b. Calculate Waiting Time of each process
Consider the following processes with arrival time and burst time. a. Draw the Gantt Chart [ 2 Marks] b. Calculate Waiting Time of each process [ 1.5 Marks] c. Calculate Total Waiting Time [0.5 Mark] d. Average waiting time [1 mark] using round robin scheduling with time quantum 2 ms? Process id Burst time (ms) QI 4 Q2 3 Q3 6 Q4 1
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts