RAM Matrix and Risk Mitigation An infrastructure development project has the following risk factors. Risk Factor, DESCRIPTION, Likelihood rating, Impact Rating A Insufficient supply of

RAM Matrix and Risk Mitigation An infrastructure development project has the following risk factors. Risk Factor, DESCRIPTION, Likelihood rating, Impact Rating A Insufficient supply of raw materials. 4, 4 B Worker injuries. 3, 3 C Extended project duration, 5, 4 D. Community disapproval of the 4, 5 project due to Resettlement issues E Water leakage, 2, 4 F. Equipment malfunction. 1, 5 LIKELIHOOD Ratings: (1) Rare, (2) Unlikely, (3) Possible, (4) Likely, (5) Almost Certain. IMPACT Ratings: (1) Insignificant, (2) Low, (3) Moderate, (4) High, (5) Catastrophic/Failure. Based on the above risk analysis:

Draw the RAM Matrix. Identify critical risk factors, moderate risk factors, and low-risk factors. For each risk factor, provide a short paragraph for Risk Mitigation to minimize the risk associated with this factor.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Long Term Care Your Financial Planning Guide

Authors: Phyllis Shelton

1st Edition

978-0963351692

More Books

Students also viewed these Finance questions

Question

4. What are the limitations of this study?

Answered: 1 week ago