randec Company manufactures, assembles, and rebuilds material handling equipment used in warehouses and distribution centers. One product, called a Liftmaster, is assembled from four components:
randec Company manufactures, assembles, and rebuilds material handling equipment used in warehouses and distribution centers. One product, called a Liftmaster, is assembled from four components: a frame, a motor, two supports, and a metal strap. Frandecs production schedule calls for Liftmasters to be made next month. Frandec purchases the motors from an outside supplier, but the frames, supports, and straps may be either manufactured by the company or purchased from an outside supplier. Manufacturing and purchase costs per unit are shown.
Three departments are involved in the production of these components. The time in minutes per unit required to process each component in each department and the available capacity in hours for the three departments are as follows:
Formulate and solve a linear programming model for this makeorbuy application. How many of each component should be manufactured and how many should be purchased? If required, round your answers to one decimal place.
Let FM number of frames manufactured
FP number of frames purchased
SM number of supports manufactured
SP number of supports purchased
TM number of straps manufactured
TP number of straps purchased
Min fill in the blank
FM fill in the blank
FP fill in the blank
SM fill in the blank
SP fill in the blank
TM fill in the blank
TP
st
FM fill in the blank
SM fill in the blank
TM fill in the blank
fill in the blank
FM SM fill in the blank
fill in the blank
FM fill in the blank
SM TM fill in the blank
FM fill in the blank
FP fill in the blank
SM fill in the blank
SP fill in the blank
TM fill in the blank
TP fill in the blank
FM FP SM SP TM TP
Manufacture Purchase
Frames fill in the blank
fill in the blank
Supports fill in the blank
fill in the blank
Straps fill in the blank
fill in the blank
What is the total cost of the manufacturing and purchasing plan? When required, round your answer to the nearest dollar.
$ fill in the blank
How many hours of production time are used in each department?
Department Hours of production
time used
Cutting fill in the blank
hours
Milling fill in the blank
hours
Shaping fill in the blank
hours
How much should Frandec be willing to pay for an additional hour of time in the shaping department?
$ fill in the blank
Another manufacturer has offered to sell frames to Frandec for $ each. Could Frandec improve its position by pursuing this opportunity?
Why or why not?
The input in the box below will not be graded, but may be reviewed and considered by your instructor.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started