rane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $ 2.8 million beginning September 1, 2020,

rane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $ 2.8 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period.

2020 2021 2022
Costs to date $ 833,000 $ 1,801,800 $ 2,346,000
Estimated costs to complete 1,617,000 538,200 0
Progress billings to date (non-refundable) 897,000 2,296,000 2,800,000
Cash collected to date 733,000 2,167,000 2,800,000

(a)

Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Report On Trade Conditions In China

Authors: Harry R. Burrill, Raymond F. Crist

1st Edition

1138617806, 9781138617803

More Books

Students also viewed these Accounting questions

Question

Explain the Pascals Law ?

Answered: 1 week ago

Question

What are the objectives of performance appraisal ?

Answered: 1 week ago

Question

State the uses of job description.

Answered: 1 week ago