Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Read the case study and answer the 4 question that are at the end of case study. Program Monitoring and Controlling Process 326 Figure 17.2

Read the case study and answer the 4 question that are at the end of case study.

image text in transcribedimage text in transcribedimage text in transcribed
Program Monitoring and Controlling Process 326 Figure 17.2 is the Earned Value Chart of the recently closed-out Xtra program The program objective was to develop a set of marketing projects for DXT's postpaid customer segment over a period of three months. WHAT WENT WRONG? Trying to understand what went wrong and the earned value concept better for future programs, the team looked back at the history of the Earned Value Chart. Although the Xtra program status appeared to be ahead of the schedule and budget plans at the beginning, the turning point was around December 21, the long vacation period, because of a lack of the company's clear direction. Since then, things got worse as the program progressed. As an effort to recover the pro- gram status, the Xtra program team tried to cut down several program scopes with hopes of improving the earned value. But problems never ceased coming. In the end, the program was not fully able to recover, and less work was accomplished than planned. In other words, the program was not able to deliver its full results. Eventually, the program was called off. At the termination time (February 22), the program was behind both schedule and budget. The Xtra program ended up spending $10.000, but only accomplished $8,600 worth of work, while the fore- casted budget at completion was $13000 (March 8). One major lesson learned was that in implementing the earned value concept both the Schedule Performance Index (SPD) and Cost Performance Index (CPI) Figure 17.2 The Earned Value Chart of the Xtra Program Planned Actual C Feb 15 Fels 22That Which Is Not Earned Is Never Valued Sabin Srivannaboon DXT Famous for its reliable service and low price campaigns, DXT was one of the well-known mobile operators in the area. The company customer base comprises prepaid customers, and it was doing well in this territory. To take the company into another level, the management team started looking at expanding the com- pany business into an uncharted area- the postpaid customer segment. DXT was a program-driven company. Last year, DXT initiated more than 40 programs, addressing various issues from the organizational structure to the competition perspectives. This year, many programs were dedicated to the post- paid customer segment as efforts in diversifying the company business. However, the postpaid customer segment was something that DXT wasn't familiar with. And the company was still unclear as to what competitive advantage it would and should provide to its postpaid customers. As a result, several programs were mov- ing in different directions, and the company ended up nowhere. The deadlines for many programs were clearly defined from the beginning. Nevertheless, DXT failed to provide a clear idea of what kind of strategies and actions they really wanted to see. Eventually. many programs failed. The lack of the alignment seemed to be a major issue at DXT these days. XTRA AND THE EARNED VALUE CONCEPT Xtra was a program that was carried out at the end of the year. Because of its strategic importance, the program delay wasn't acceptable. To make sure the pro- gram would be completed on time, the program team decided to use the Earned Value concept. Although it was a good intention, the program team faced one big challenge: the earned value concept had never been implemented in the company before. And as one could expect, the team ran into multiple problems and difficul ties not only in managing the program itself, but also understanding and using the earned value concept. 324326 CASE STUDIES were important indicators to watch, but the CPI was clearly the more sensitive factor because a poor CPI was likely to be nonrecoverable. The program team should have monitored closely the trend of the CPI throughout the program life cycle. The SPI, on the other hand, was more important during the early phases. but became less significant as the program neared completion. Discussion items Analyze the program history and calculate the program schedule performand index (SPD) and the program cost performance index (CPI) at different major points in time of the program life cycle. What could have been done when the cost and time overruns were detected? What would be the major challenges in implementing the earned value concept? How can such challenges be overcome? Why does the SPI become less significant as the program neared completion

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Welcome To Hospitality An Introduction

Authors: Kaye Kye-Sung Chon, Thomas A. Maier

3rd Edition

1111780684, 9781111780685

More Books

Students also viewed these General Management questions