Read the case study below and answer ALL the questions that follow. Lockdown forcing construction sector to think more strategically about tech adoption According to

Read the case study below and answer ALL the questions that follow.
Lockdown forcing construction sector to think more strategically about tech adoption
According to the results of a survey conducted by Construction Computer Software (CCS) amongst its clients,
stakeholders and industry partners, the lockdown has compelled the construction industry to think more strategically
about the adoption of technology, especially as it relates to communication and collaboration. The survey was
conducted to establish how the construction industry has been affected by the lockdown and what measures players
are putting in place to manage the current situation, as the sector is expected to play a major role in South Africa's
economic recovery post the Covid-19 pandemic. Project disruptions and delays
Some 70% of respondents said all their projects have been affected by disruptions or delays due to the Covid-19
pandemic and 52% of respondents from companies with a revenue of more than R 1bn indicated that 100% of their
projects have been delayed or disrupted. These disruptions and delays are as a result of the lockdown measures
enforced by government, as well as shortages of materials, plants and equipment and PPE.
CCS CEO Andrew Skydder says while respondents expect all construction sectors to be affected by the pandemic
in the short-term, the building sector is expected to be the most affected.
"The building sector is primarily funded by private sector clients, who are expected to cut back on investments due
to the anticipated economic decline as a result of the Covid-19 pandemic. Residential and retail investment is likely
to be most affected due to significant job losses, growing consumer financial stress and a lack of confidence
following the Covid-19 enforced lockdowns."
He adds that infrastructure spending, including civil and roads, is expected to be less affected as this tends to be
government funded. "Respondents suggest that government is likely to accelerate its infrastructure spend
programme in a bid to accelerate economic recovery and absorb unemployed labour into the employment market
as quickly as possible. Mining is expected to be least affected."
Private clients most affected
79% of respondents said private clients would be the most affected. Business and consumer confidence have been
negatively affected by the Covid-19 pandemic and lockdowns, which is expected to result in a 6.1% decline in GDP
in 2020. This supports the view that the building sector will be most affected as it is primarily funded by private
clients.
State-owned enterprises, such as Eskom and Sanral, are expected to be least affected. Eskom, in particular, is an
essential service provider and has significant build programmes under way which have not been affected by the
lockdown. In addition, water authorities such as Rand Water, which is an extension of national government, are
also expected to be less affected as they too provide essential services, with infrastructure requiring ongoing
maintenance and upgrading.
Skudder says 77% of respondents indicated that on more than 20% of their projects, clients have invoked force
majeure clauses on their projects. "Smaller companies seem to have been less affected with 67% of companies
with less than R100m revenue having more than 20% of their projects affected." "This compares to 89% of R 100m
to R500m,79% of R500m to R1bn and 80% of R1bn-plus revenue companies. Companies with a revenue of
between R100m and R1bn seem to have had the highest level of force majeure being invoked, with 57% of R100m
to R 500m companies having 81% to 100% of their projects being affected, compared to just 20% for companies
with revenue of less than R1bn.
Managing the challenges presented by the pandemic
Skydder says a few major themes emerged in the survey. "One was the increased need to keep the channels of
communication open, especially with employees, but also with clients and other stakeholders on projects. It is
undoubtedly healthier for businesses if people feel informed in times of great uncertainty. "Cost management is
another obvious theme, with companies implementing measures to manage costs and ensure liquidity stretches for
as long as possible. Interestingly, organisation
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Time Management For Writers

Authors: Katie Forrest

1st Edition

1711795860, 978-1711795867

More Books

Students also viewed these General Management questions

Question

7.3 Describe considerations in the preliminary applicant screening.

Answered: 1 week ago

Question

7.2 Explain the selection process.

Answered: 1 week ago