Question
Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering
Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities:
Activity | Normal Time (weeks) | Crashed Time (weeks) | Normal Cost | Crashed Cost | Predecessor(s) |
---|---|---|---|---|---|
A | 3 | 2 | $1,050 | $3,300 | - |
B | 6 | 5 | $2,080 | $2,460 | - |
C | 3 | 1 | $1,300 | $2,800 | - |
D | 7 | 3 | $2,000 | $2,500 | A |
E | 6 | 3 | $1,500 | $2,100 | B |
F | 3 | 2 | $4,100 | $5,420 | C |
G | 4 | 2 | $1,650 | $2,100 | D, E |
What is the overall duration of the project?
Which activities have the lowest crash cost per week?
Which activities have the highest crash cost per week?
If you wanted to shorten the overall duration of the project, which activity should you crash first?
What is the total cost of crashing the project from its current duration down to 13 weeks?
What is the total cost of crashing the project from its original duration to 11 weeks?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
The overall duration of the project can be determined by identifying the longest path also known as the critical path which consists of activities that must be completed in sequence without any delays ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started