> Realize Your Potential: Learn. Perf X C dau.csod.com/Evaluations/EvalLaunch.aspx?loid=94c6e0d0-1869-4 TO1.EO5 Identify techniques used by agile teams to estimate softwa Question 2 of 20. Which
> Realize Your Potential: Learn. Perf X C dau.csod.com/Evaluations/EvalLaunch.aspx?loid=94c6e0d0-1869-4 TO1.EO5 Identify techniques used by agile teams to estimate softwa Question 2 of 20. Which role from the scrum team always estimates the PBIs during Planning Poker? O Scrum Master O Product Owner O Project Manager (PM) Development Team Mark for follow up < < Back Save / Return Later Summary Next >>