Recently, Phil Harris, the production control manager at Brunswick, read an article on time - phased requirements planning. He was curious about how this technique
Recently, Phil Harris, the production control manager at Brunswick, read an article on timephased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of timephased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model engine. This schedule indicates the number of units of the Model engine to be assembled each week during the last weeks and is shown on the next page. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model engine. These two components, the gear box and the input shaft, are shown in the product structure diagram below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine assembly line. The input shaft is one of several component parts manufactured by Brunswick that are needed to produce a gear box subassembly. Thus, levels and are included in the product structure diagram to indicate the three manufacturing stages that are involved in producing an engine: the Engine Assembly Department, the Subassembly Department, and the Machine Shop.
The manufacturing lead times required to produce the gear box and input shaft components are also indicated in the product structure diagram. Note that two weeks are required to produce a batch of gear boxes and that all the gear boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of input shafts, and all the shafts that are needed for the production of gear boxes in a given week must be delivered to the Subassembly Department stockroom before Monday morning of that week.
a Inltially, assume that Phil wants to minimize his Inventory requirements. Assume that each order will be only for what is required for a
single period. Calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is
done using lotforlot LLLeave no cells blank be certaln to enter wherever requlred.
Gear Box Requlrements
Input Shaft RequirementsIn preparing the MRP example Phil planned to use the worksheets shown and to make the following assumptions:
Twenty gear boxes are on hand at the beginning of Week and six gear boxes are currently on order to be delivered at the start of Week two.
Forty input shafts are on hand at the start of Week and are scheduled for delivery at the beginning of Week
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started