Answered step by step
Verified Expert Solution
Question
1 Approved Answer
red x is wrong please answer in same format as homework Required Information [The following information applies to the questions displayed below.] In 2021, the
red x is wrong please answer in same format as homework
Required Information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $3,649, 280 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,581,800 6,319,888 2,090, eee 1,845,000 2022 $2,347,880 2,772,eee 2,838, eee 2,900,000 5,672,000 5,255, eee Westgate recognizes revenue over time according to percentage of completion. 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round Intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be Indicated with a minus sign.) 2021 $2,581,898 6,319,000 Costs incurred during the year Estimated costs to complete as of year-end 2022 $3,845, eee 4,190, eee 2023 $4,835,600 Answer is complete but not entirely correct. 2022 2023 3.948.873 IS 2021 2.900.000 319,000 Revenue Gross profit (loss) IS 3,153,127 Is (691.873) XS IS IS (88,127) XStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started