Reducing the amount of safety time added to individual tasks and using some fraction of that reduction as a safety buffer for the entire project
Reducing the amount of safety time added to individual tasks and using some fraction of that reduction as a safety buffer for the entire project is known as the _____________. PERT/CPM model float time excess capacity Project buffer