Reducing the duration ofa project individual Use the information contained below to compress one time unit per move using the least cost method. Reduce the
Reducing the duration ofa project individual Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed the crash cost. Activity Predecessor Normal Time Max Crash Crash Cost Time 0 0 A None 1 B A 3 2 100 C A 4 1 50 D B 3 1 60 E C 4 2 70 F D, E 3 1 90