Question
1 Approved Answer
Reducing the project duration increases the risk of being late because reducing the slack of noncritical activities increases the likelihood of creating new critical paths.
Reducing the project duration increases the risk of being late because reducing the slack of noncritical activities increases the likelihood of creating new critical paths. More critical paths increase the risk of the project being late. Shortening the critical path can save money in instances where indirect costs are a significant percentage of total project costs. A shorter project means these costs are incurred for less time. rewrite these