Refer to the Table 1 and do the following: Calculate the Expected time, meantime. Develop the Network diagram using the expected time and use PERT
Refer to the Table 1 and do the following:
- Calculate the Expected time, meantime.
- Develop the Network diagram using the expected time and use PERT Analysis to know the mean and Sd of the project.
- Based on these estimates and the resultant expected project duration of 69 days. Does the executive committee want to know what is the probability of completing the project before a scheduled time of 68 days?
- How do you measure project risk exposure? Explain and propose ways to reduce the project risk exposure.
(maximum 500 words)
Table 1: All O, ML, P are on workdays.
Activity No | Task Name | Optimistic Duration(O) | Most Likely Duration(ML) | Pessimistic Duration(P) | Immediate Predecessor |
1 | Team meeting | 0.5 | 1 | 1.5 | |
2 | Hire Contractors | 6 | 7 | 8 | 1 |
3 | Network Design | 12 | 14 | 16 | 1 |
4 | Order Ventilation system | 18 | 21 | 30 | 1 |
5 | Install Ventilation system | 5 | 7 | 9 | 4 |
6 | Order new racks | 13 | 14 | 21 | 1 |
7 | Install racks | 17 | 21 | 25 | 6 |
8 | Order power supplies and cables | 6 | 7 | 8 | 1 |
9 | Install power supplies | 5 | 5 | 11 | 8,12 |
10 | Install cables | 6 | 8 | 10 | 8,12 |
11 | Renovation of data centre | 19 | 20 | 27 | 2,3 |
12 | City inspection | 1 | 2 | 3 | 2,5,7 |
13 | Facilities | 7 | 8 | 9 | 10 |
14 | Operations/System | 5 | 7 | 9 | 10 |
15 | Operations/Telecommunications | 6 | 7 | 8 | 10 |
16 | System & applications | 7 | 7 | 13 | 10 |
17 | Customer service | 5 | 6 | 13 | 10 |
18 | Power check | 0.5 | 1 | 1.5 | 9,10,11 |
19 | Install test servers | 5 | 7 | 9 | 1,2,13,14,15,16 |
20 | Management safety check | 1 | 2 | 3 | 5,18,19 |
21 | Primary systems check | 1.5 | 2 | 2.5 | 20 |
22 | Set date for the move | 1 | 1 | 1 | 21 |
23 | Complete move | 1 | 2 | 3 | 22 |
Part 4-Outcomes-1 mark | Marks | Page Number |
PERT calculation model with a description | ||
Project Duration means of the project, Sd of the Project, | ||
Probability of 68 days duration | ||
Step by Step Solution
3.40 Rating (159 Votes )
There are 3 Steps involved in it
Step: 1
Answer Solution There are two Critical paths 1671210131920212223 and 1671210161920212223 Expected pr...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started