Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

refund will ya Time (weeks) 15 5 6 7 8 9 10 11 16 17 18 2 3 4 A (5 weeks) C (5 weeks)

image text in transcribed
image text in transcribed
refund will ya
Time (weeks) 15 5 6 7 8 9 10 11 16 17 18 2 3 4 A (5 weeks) C (5 weeks) E (3 weeks) 12 13 B (10 weeks) D(10 weeks) G ( 3 weeks) F (10 weeks) The schedule of a small steel bridge project and the activities budget cost are shown below. At the end of the 8thweek, the field progress report gives you the following information: Activities "A" and "C" were completed as planned. Activity "B" started as planned and still in progress Activity "D" started as planned but it is expected to take three more weeks. Due to limited resources. Activity "E" did not start until the completion of activity A. The actual expenses by the end of the sweek - SR 20000 B D E F G 1000 3000 1470 0 1575.2 1400 1300 Activity Material Budgeted Cost (SR) Equipment Budgeted Cost Site Overheads (SR) 435 0 840 17250 4500 8000 0 0 1950 388 1005 110 0 200 Assume that the planned percentage of completion for each activity is uniformly distributed over the activity duration except for activity F that has the following per period planned percentage of completion: Period Planned Precentage of Completion 2 3 4 5 6 7 8 9 10 10 12 10 8 13 8 8 19 10 2 As you are the project manager, the project owner(ie course tutor) request you to answer the following questions What is the cost Variance by the end of week 8? What is the schedule variances by the end of week 8? Based on the project performance over the past 8 weeks, what is the anticipated project costat completion? Based on the project performance over the past 8 weeks, what is the status of the project in term of time? Based on the project performance over the past 8 weeks, what is the status of the project in term of cost? Time (weeks) 15 5 6 7 8 9 10 11 16 17 18 2 3 4 A (5 weeks) C (5 weeks) E (3 weeks) 12 13 B (10 weeks) D(10 weeks) G ( 3 weeks) F (10 weeks) The schedule of a small steel bridge project and the activities budget cost are shown below. At the end of the 8thweek, the field progress report gives you the following information: Activities "A" and "C" were completed as planned. Activity "B" started as planned and still in progress Activity "D" started as planned but it is expected to take three more weeks. Due to limited resources. Activity "E" did not start until the completion of activity A. The actual expenses by the end of the sweek - SR 20000 B D E F G 1000 3000 1470 0 1575.2 1400 1300 Activity Material Budgeted Cost (SR) Equipment Budgeted Cost Site Overheads (SR) 435 0 840 17250 4500 8000 0 0 1950 388 1005 110 0 200 Assume that the planned percentage of completion for each activity is uniformly distributed over the activity duration except for activity F that has the following per period planned percentage of completion: Period Planned Precentage of Completion 2 3 4 5 6 7 8 9 10 10 12 10 8 13 8 8 19 10 2 As you are the project manager, the project owner(ie course tutor) request you to answer the following questions What is the cost Variance by the end of week 8? What is the schedule variances by the end of week 8? Based on the project performance over the past 8 weeks, what is the anticipated project costat completion? Based on the project performance over the past 8 weeks, what is the status of the project in term of time? Based on the project performance over the past 8 weeks, what is the status of the project in term of cost

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Production And Operations Analytics

Authors: Steven Nahmias, Tava Lennon Olsen

8th Edition

1478639261, 9781478639268

More Books

Students also viewed these Finance questions