Republic Tool and Manufacturing Company of Carlsbad, California, makes a wide variety of lawn care products. One of Republic's products is the Model Number 540

image text in transcribedimage text in transcribed

Republic Tool and Manufacturing Company of Carlsbad, California, makes a wide variety of lawn care products. One of Republic's products is the Model Number 540 Broadcast Spreader. Complete the following MRP records. Note the following:

Republic intends to start assembling 1,000 broadcast spreader kits in weeks 2, 4, and 6.

The gross requirements for the gear and rotor plate assembly have already been given to you. For the remaining items, you will need to figure out the gross requirements.

All scheduled receipts, lead times, and beginning inventory levels are shown.

Note that cotter pins appear twice in the bill of material.

Construct the material requirements plan for item Gear and rotor plate assembly (enter your responses as whole numbers).

image text in transcribed
Republic Tool and Manufacturing Company of Carlsbad, California, makes a wide variety of lawn care products. One of Republic's products is the Model Number 540 Broadcast Spreader. Complete the following MRP records. Note the following: - Republic intends to start assembling 1,000 broadcast spreader kits in weeks 2,4 , and 6. - The gross requirements for the gear and rotor plate assembly have already been given to you. For the remaining items, you will need to figure out the gross requirements. - All scheduled receipts, lead times, and beginning inventory levels are shown. - Note that cotter pins appear twice in the bill of material. Click the icon to view the BOM for the Model Number 540 Broadcast Spreader. Click the icon to view the MRP records. Gear and rotor plate assembly: Lead Time =1 week; Minimum order quantity =3,900 \begin{tabular}{lcccccc} \hline Week & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline Gross requirements & & 1,000 & & 1,000 & & 1,000 \end{tabular} Scheduled receipts Projected ending inventory: 700 Net requirements Planned receipts Planned orders Wheels: Lead Time =1 week; Minimum order quantity =3,700 \begin{tabular}{lllllll} \hline Week & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline Gross requre \end{tabular} Gross requirements Scheduled receipts Projected ending inventory: 1,900 Net requirements Planned receipts Planned orders Cotter pins: Lead Time =4 weeks; Minimum order quantity =27,500 \begin{tabular}{lllllll} \hline Week & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline \end{tabular} Gross requirements Scheduled receipts Projected ending inventory: 6,000 Net requirements Planned receipts

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Sustainability And Supply Chain Management

Authors: Jay Heizer, Barry Render, Chuck Munson, Paul Griffin

3rd Canadian Edition

0134838076, 978-0134838076

More Books

Students also viewed these General Management questions

Question

Describe in detail the steps of the IRAC legal analysis process.

Answered: 1 week ago

Question

What were the causes of the Industrial Revolution in England ?

Answered: 1 week ago