Question

1 Approved Answer

Requested daily quantity for a product is 5 0 0 units ( defect free ) . The production times ( given as normal time )

Requested daily quantity for a product is 500 units (defect free). The production times (given as normal time) of the two operations respectively are as follows: Operation a=2min/unit; Operation b=10min/unit. The defect rates is given as 20% for Operation a and 30% for Operation b in serial. Workers assigned to these operations will accomplish the conversions. The performance of the individual employee are expected to be 90%. There are two scenarios:
Scenario I: With Rework
Although the defect rates are given, no product is permitted to leave the plant with any quality defects. Accordingly, all of the defects must be corrected, and the average time to correct the defect is 150% of the initial conversion time. The same work teams will accomplish this rework. The plant is run as a one-shift 8 hr/day (meal break of 30 min (unpaid); Short Breaks 2*15min; downtime=45min) operation.
Scenario II:Without Rework
There is no rework. The plant is run as a one-shift 8 hr/day (meal break of 30 min (unpaid); Short Breaks 2*15min; downtime=45min) operation. c) If there is a 10% of Efficiency of the line (=Performance of the line)(by using an incentive system based on perfomance) what will the effect on OEE? (Hint: OEE; w; Assignment etc)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Retailing Management

Authors: Levy, Weitz

9th Edition

1259060667, 9781259060663

More Books

Students also viewed these General Management questions