Question
Required : Calculate the price variance for materials based on the actual purchase. Calculate the efficient variance for materials based on production. Calculate the price
- Required: Calculate the price variance for materials based on the actual purchase.
Calculate the efficient variance for materials based on production.
Calculate the price variance for materials based on production.
Calculate the efficient variance for materials based on production.
The industrial engineer had established the following standard for producing sweatshirts.
Direct Materials 3 square yards at $ 1.50 per square yard
Direct Labor 1.5 hours at $ 6 per hour.
During the period actual results were as follows
Sweatshirts Produced 100,000
Direct Materials Used 303,000 square yards at $ 1.60 per square yard
Direct Materials Purchased 320,000 square yards at $ 1.60 per square yard
Direct Labor 142,000 hours at $ 6.10 per hour.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started