Determine the following :a. Calculation of estimated total labor that was expected for 20XX. (expected persons times hours times rate)b. Predetermined overhead rate for year 20XX.c. Overhead cost applied to each of the six jobs during year 20XX.d. Over or underapplied at year-end 20XX.Assuming that any over- or underapplied overhead is not material, prepare the adjusting entry allocate anyover- or underapplied overhead to Cost of Goods Sold at the end of year 20XX.Hint: COGS has a $18,420 credit balance at year end.

Bigsby Company's manager estimated 20XX's total direct labor cost assuming 100 persons working an average of 2,000 hours each at an average wage rate of $18 per hour. The manager also estimated the following manufacturing overhead costs for year 20XX. Indirect labor Factory supervision $ 319,200 240,000 Rent on factory building 140,000 Factory utilities 100,000 Factory insurance expired 68,000 Depreciation--Factory equipment 480,000 Repairs expense--Factory equipment 60,000 Factory supplies used 68,800 Miscellaneous production costs 36,000 Total estimated overhead costs $ 1,512,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Income Tax Fundamentals 2013

Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill

31st Edition

1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516

More Books

Students also viewed these Accounting questions