Question

1 Approved Answer

Required information Problem 6 - 1 0 ( Algo ) Long - term contract; revenue recognition over time [ LO 6 - 8 , 6

Required information
Problem 6-10(Algo) Long-term contract; revenue recognition over time [LO6-8,6-9]
Skip to question
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
202420252026
Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800
Estimated costs to complete as of year-end 5,256,0002,628,0000
Billings during the year 2,170,0002,502,0005,328,000
Cash collections during the year 1,885,0002,600,0005,515,000
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10(Algo) Part 5
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information.
Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.
202420252026
Costs incurred during the year $ 2,044,000 $ 3,885,000 $ 4,155,000
Estimated costs to complete as of year-end 5,256,0004,270,0000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions