Question
Required information Skip to question [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to
Required information
Skip to question
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
| 2021 | 2022 | 2023 | ||||||
Cost incurred during the year | $ | 2,204,000 |
| $ | 3,192,000 |
| $ | 2,424,400 |
|
Estimated costs to complete as of year-end |
| 5,396,000 |
|
| 2,204,000 |
|
| 0 |
|
Billings during the year |
| 2,140,000 |
|
| 3,256,000 |
|
| 4,604,000 |
|
Cash collections during the year |
| 1,870,000 |
|
| 3,200,000 |
|
| 4,930,000 |
|
Westgate recognizes revenue over time according to percentage of completion.
Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.) 2021 Revenue ???
2021 Gross profit (loss) ???
2022 Revenue ???
2022 Gross profit (loss) ???
2023 Revenue ???
2023 Gross profit (loss) ???
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started