Required information The following information applies to the questions displayed below.) A manufactured product has the following information for June Direct materials Direct labor Overhead Units manufactured Standard Quantity and cost 5 pounds @ $9 per pound 3 DLH @ $16 per DLH 3 DLH @ $12 per DLH Actual Results 35,500 pounds @ $9.10 per pound 20,600 hours @ $16.50 per hour $ 257,500 7,000 units (1) Prepare the standard cost card showing standard cost per unit. (2) Compute total budgeted cost for June production (3) Compute total actual cost for June production (4) Compute total cost variance for June. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Prepare the standard cost card showing standard cost per unit. Direct materials Direct labor Overhead Total $ 0 Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Standard Quantity and Cost Actual Results Direct materials 5 pounds @ $9 per pound 35,500 pounds @ $9.10 per pour Direct labor 3 DLH @ $16 per DLH 20,600 hours @ $16.50 per hour Overhead 3 DLH @ $12 per DLH $ 257,500 Units manufactured 7,000 units (1) Prepare the standard cost card showing standard cost per unit. (2) Compute total budgeted cost for June production. (3) Compute total actual cost for June production. (4) Compute total cost variance for June. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Compute total budgeted cost for June production. Total budgeted (standard) cost Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard Quantity and Cost 5 pounds @ $9 per pound 3 DLH @ $16 per DLH 3 DLH @ $12 per DLH Actual Results 35,500 pounds @ $9.10 per pound 20,600 hours @ $16.50 per hour $ 257,500 7,000 units (1) Prepare the standard cost card showing standard cost per unit (2) Compute total budgeted cost for June production. (3) Compute total actual cost for June production (4) Compute total cost variance for June. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required Required 4 Compute total actual cost for June production Actual cont Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard Quantity and cost 5 pounds @ $9 per pound 3 DLH @ $16 per DLH 3 DLH $12 per DLH Actual Results 35,500 pounds @ $9.10 per pound 20,600 hours @ $16.50 per hour $ 257,500 7,000 units (1) Prepare the standard cost card showing standard cost per unit. (2) Compute total budgeted cost for June production. (3) Compute total actual cost for June production. (4) Compute total cost variance for June. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required Compute total cost variance for June. (Indicate the effect of the variance by selecting favorable, unfavorable, or no variance.) Total cost variance (Required 3 Required