[The following information applies to the questions displayed below.] A manufactured product has the following information for June.
Standard Quantity and Cost | Actual Results | ||
---|---|---|---|
Direct materials | 6 pounds @ $8 per pound | 48,500 | pounds @ $8.10 per pound |
Direct labor | 2 DLH @ $16 per DLH | 15,700 | hours @ $16.50 per hour |
Overhead | 2 DLH @ $12 per DLH | $ 198,000 | |
Units manufactured | 8,000 | units |
Exercise 8-8 (Static) Standard cost per unit, total budgeted and actual costs, and total cost variance LO P2
(1) Prepare the standard cost card showing standard cost per unit. (2) Compute total budgeted cost for June production. (3) Compute total actual cost for June production. (4) Compute total cost variance for June.
AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price
AH = Actual Hours SH = Standard Hours AR = Actual Rate SR = Standard Rate
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started