research paper: Build a Network Diagram for developing a clincial trial management software The first step in building the network diagram is sequencing all of
research paper: Build a Network Diagram for developing a clincial trial management software
The first step in building the network diagram is sequencing all of the activities.
A completed network diagram enables you to able to determine: a project's scheduled completion time, the slack or float of project activities, and the critical path of your project.
Build a Project Network or a Partial Network
Brainstorm the activities required to complete the work packages. Record on note cards or Postit notes. Dont worry about the order or sequence.
Sequence the note cards or Postit notes with the activities. Determine:
The order of activities
Which activities can occur in parallel
Which activities require dependencies
Mandatory: before the activity can begin or end the completion of another task is required.
Discretionary: a best practice or convenience. However, the subsequent task can begin if the discretionary dependency is not completed.
External: requires additional project or process, such as permits.
Internal: dependencies within the control of the project team.
Place the notes on a wall based steps and
Build a network based on step.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started