Resource Management Plan Project Name : To host a webinar on Project Management Project Sponsor : Project Management Services Company Project Duration: 6 weeks Project

Resource Management Plan

Project Name: To host a webinar on Project Management

Project Sponsor: Project Management Services Company

Project Duration:6 weeks

Project Start Date: 30-01-2023

Project End Date: 10-03-2023

Resource Identification:The following resources are required to host a webinar on Project Management:

  • Human Resources:
    • A host who is knowledgeable in the given topic and can conduct a webinar
    • Attendees who are interested in learning about Project Management
    • Volunteers who are capable of assisting the attendees and collecting feedback from them after the sessions are finished
    • Audio & Video Technicians to take care of any issues during the seminar

  • Physical Resources:
    • Computers and other peripherals
    • Audio and video equipment
    • Cameras to record the sessions
    • Power Backup to all the equipment
    • A good internet connection

Resource Control:

  • For the project to be a success it is important that is completed within the allotted budget of$CAD 10,000 and within the stipulated timeframe of6 weeks
  • Ensure that the cost to buy the computers and other required peripherals and cameras does not exceed the budget. There must be enough room in the budget after buying the equipment to hire audio and video technicians
  • Make sure that the duration of the project does not exceed the scheduled 6 weeks
  • Inform the host, volunteers, and equipment technicians of their necessary duties throughout the project

Assumptions:

  • Physical resources like computers and cameras to work without any mechanical issues or failures
  • A host to conduct the webinar without any interruptions
  • Audience to attend and engage with the host and provide adequate feedback
  • Volunteers to efficiently assist with any issues during the sessions
  • Audio and video technicians to handle equipment issues

Constraints:

  • Project Schedule of 6 weeks might not be enough to collect necessary feedback
  • Allotted budget might not be enough to conduct the webinars
  • Equipment might malfunction during the sessions
  • Feedback might not be indicative of general interest

Resource Breakdown Structure:

image text in transcribed
Webinar on Project Management Human Physical Resources Resources Computer, Host Volunteers video and audio Peripherals

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The General Managers

Authors: John P. Kotter

1st Edition

0029182301, 978-0029182307

More Books

Students also viewed these General Management questions

Question

12.3 Explain employment termination of various occupational groups.

Answered: 1 week ago

Question

Define outplacement and severance pay.

Answered: 1 week ago

Question

What would you do?

Answered: 1 week ago