Respond to the below questions using the following data for EVM: PV: 500,000 EV: 350,000 AC: 550,000 BAC: 1,200,000 Solve: 1) Compute SV. 2)

image text in transcribed 

Respond to the below questions using the following data for EVM: PV: 500,000 EV: 350,000 AC: 550,000 BAC: 1,200,000 Solve: 1) Compute SV. 2) Compute CV. 3) Compute SPI. 4) Compute CPI. 5) What does the SPI value tell us about the project? 6) What does the CPI value tell us about the project? 7) What is the ETC? 8) What is the EAC? 9) If you were to improve CPI to a value of 1.4; what would that mean for the project? 10) If CPI were 1.4; what would be the new EAC?

Step by Step Solution

3.54 Rating (147 Votes )

There are 3 Steps involved in it

Step: 1

1 Compute SV SV EV PV SV 350000 500000 SV 150000 2 Compute CV CV EV AC CV 350000 550000 CV 200000 3 ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach To Planning Scheduling And Controlling

Authors: Harold Kerzner

12th Edition

1119165350, 9781119165354

More Books

Students also viewed these General Management questions